Multi-objective optimisation in flexible assembly job shop scheduling using a distributed ant colony system
Zhang, Sicheng1; Li, Xiang1; Zhang, Bowen1; Wang, Shouyang2
2020-06-01
发表期刊EUROPEAN JOURNAL OF OPERATIONAL RESEARCH
ISSN0377-2217
卷号283期号:2页码:441-460
摘要This paper studies the production scheduling problem in a flexible manufacturing system with two adjacent working areas, whose products are incorporated with flexible non-linear process plans and assembling operations. The basic parts are produced in one area before they are transported to the other area for assembly. The assembling structures of products are either flat or multi-levelled. Sequence-dependent setup times of operations and transition times of jobs between machines are considered separately from processing times. Lot streaming is considered beforehand such that each job represents a basic part instead of a batch of identical parts. Identical subassemblies are shared by all possible assembling operations, instead of being pre-associated with any product. Makespan, total tardiness and total workload are taken as objectives to be optimised. We propose a distributed ant colony system to solve the problem and explore the Pareto front. The approach is first compared with other methods, using several sets of hypothetical test cases with different sizes and complexities; then, it is applied to solve a ball valve production scheduling problem under different scenarios. We show that the proposed approach outperforms most of the other methods for the tested problems, especially for large-scale instances, making it a valuable and competitive approach for solving practical production scheduling problems. (C) 2019 Elsevier B.V. All rights reserved.
关键词Scheduling Flexible assembly job shop scheduling Multi-objective optimisation Meta-heuristics Ant colony optimisation
DOI10.1016/j.ejor.2019.11.016
收录类别SCI
语种英语
资助项目National Natural Science Foundation of China[71722007] ; National Natural Science Foundation of China[71901015] ; National Natural Science Foundation of China[71931001] ; Funds for First-class Discipline Construction[XK18025] ; Fundamental Research Funds for the Central Universities[buctrc201926]
WOS研究方向Business & Economics ; Operations Research & Management Science
WOS类目Management ; Operations Research & Management Science
WOS记录号WOS:000515445500003
出版者ELSEVIER
引用统计
文献类型期刊论文
条目标识符http://ir.amss.ac.cn/handle/2S8OKBNM/50844
专题系统科学研究所
通讯作者Li, Xiang
作者单位1.Beijing Univ Chem Technol, Coll Econ & Management, 15 North 3rd Ring Rd East, Beijing 100029, Peoples R China
2.Chinese Acad Sci, Acad Math & Syst Sci, 55 Zhongguancun East Rd, Beijing 100190, Peoples R China
推荐引用方式
GB/T 7714
Zhang, Sicheng,Li, Xiang,Zhang, Bowen,et al. Multi-objective optimisation in flexible assembly job shop scheduling using a distributed ant colony system[J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH,2020,283(2):441-460.
APA Zhang, Sicheng,Li, Xiang,Zhang, Bowen,&Wang, Shouyang.(2020).Multi-objective optimisation in flexible assembly job shop scheduling using a distributed ant colony system.EUROPEAN JOURNAL OF OPERATIONAL RESEARCH,283(2),441-460.
MLA Zhang, Sicheng,et al."Multi-objective optimisation in flexible assembly job shop scheduling using a distributed ant colony system".EUROPEAN JOURNAL OF OPERATIONAL RESEARCH 283.2(2020):441-460.
条目包含的文件
条目无相关文件。
个性服务
推荐该条目
保存到收藏夹
查看访问统计
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Zhang, Sicheng]的文章
[Li, Xiang]的文章
[Zhang, Bowen]的文章
百度学术
百度学术中相似的文章
[Zhang, Sicheng]的文章
[Li, Xiang]的文章
[Zhang, Bowen]的文章
必应学术
必应学术中相似的文章
[Zhang, Sicheng]的文章
[Li, Xiang]的文章
[Zhang, Bowen]的文章
相关权益政策
暂无数据
收藏/分享
所有评论 (0)
暂无评论
 

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。